What is a common result of conflicts in stakeholder requirements?

Study for the IIBA BABOK v3 Exam. Engage with flashcards and multiple-choice questions, each with hints and explanations. Boost your exam readiness!

When conflicts arise in stakeholder requirements, a typical outcome is scope infeasibility and project delays. This situation occurs because conflicting requirements can complicate the project scope, making it challenging to define what the project should deliver.

When stakeholders have differing expectations or needs, it can lead to ambiguity about the project's objectives. This lack of clarity can cause significant delays as the team may need extra time to negotiate, clarify, and reconcile the differences in requirements. Such conflicts can also result in adjustments to the project scope, requiring additional resources, time for analysis, and revisions, further pushing back timelines and potentially jeopardizing the successful completion of the project.

Therefore, understanding how to manage and resolve these conflicts is critical for ensuring projects stay on track and meet stakeholder expectations without sacrificing quality or feasibility.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy